| Client | Touro University |
|---|---|
| Location | Vallejo, California |
| Project type | Campus building renovation |
| Occupied during work | No |
| Building | University campus building, renovation |
| Scope | Cabling, IT room, wireless, fiber backbone |
| Backbone | Fiber, spliced, terminated and OTDR tested |
| Coordination | Around campus operations and calendar |
| Closeout | Test results, OTDR traces, as-builts |
| License | CSLB #472017, C-7 Low Voltage Systems |
Touro University: tying a renovated building into the campus backbone
Touro University in Vallejo renovated one of its campus buildings. Our low voltage scope on that renovation covered four systems: network cabling throughout the building, the buildout of the IT room that serves it, a wireless network, and the fiber backbone connecting the building to the rest of the campus.
A building on a campus doesn’t stand on its own. Its network had to plug into a campus that already had standards for cabling category, labeling, rack layout and wireless platform. Its backbone also had to land in campus telecommunications infrastructure that already existed. On top of that, the campus kept operating during the renovation, so we coordinated the work with the university around its calendar and the activity in the surrounding buildings. Telelink Business Services is a licensed C-7 Low Voltage Systems Contractor, CSLB License #472017. Our approach to education work is based on this project.
What we installed at Touro University
Fiber backbone. A fiber optic backbone connecting the renovated building to the campus network. We installed it to ANSI/TIA-568.3-D, following outside plant practice per TIA-758 where the route left the building, and spliced and terminated it at both ends. We tested it with an OTDR and with a light source and power meter, so the traces and loss figures could be delivered with the closeout.
Network cabling. Horizontal cabling from the IT room to the classroom, office, lab, wireless and equipment locations in the building. It was installed to ANSI/TIA-568.2-E with the cable rating the ceilings required, supported on pathway sized for the drop count, firestopped at rated penetrations, and labeled to the university’s scheme.
IT room buildout. We built the IT room to TIA-569 and the campus standard, with backboard, racks, ladder rack, fiber and copper patch panels, cable management, and a bonding busbar with the racks and ladder rack bonded per TIA-607. Dedicated circuits and the bond from the busbar to the building grounding electrode system were the electrician’s scope.
Wireless network. We designed a managed wireless network for the building from a site survey of the finished spaces, cabled each access point location, and configured it on the platform the university’s IT department specified.
How the work was phased
Inside the building, the renovation schedule set the order of work. We set pathway, boxes and sleeves during framing. We pulled and dressed cable after drywall and before the ceilings closed, in time for the above-ceiling inspection. The IT room was built out ahead of the network equipment delivery, so the university’s switches could be racked, patched and uplinked as soon as they arrived.
The backbone ran on its own schedule. Fiber between buildings depends on the campus pathway, so we confirmed the route, the conduit fill and the entrance points with the university before ordering cable. We also scheduled the splicing and testing at the campus end with the university’s IT staff, to avoid disturbing the existing network. Outside the renovated building, we coordinated with campus operations. The crew checked in and identified themselves according to the university’s rules and stayed clear of the areas in use. Terminations, testing and labeling were completed room by room, and once the access points were live, we validated the wireless with a walk test.
What the owner received at closeout
At turnover, the university received:
- Permanent link test results for every copper drop, in the tester’s native format and as PDF, organized by the labeling scheme.
- OTDR traces and loss measurements for the backbone fiber strands.
- As-built drawings showing outlet, access point, pathway, backbone route and equipment locations.
- Rack elevations and patch panel schedules for the IT room, including the fiber panel.
- A labeling schedule matching every outlet, panel and cable, following TIA-606.
- Wireless validation results and the access point configuration record.
- Manufacturer documentation and warranty letters for the installed equipment.
Next step
If your campus has a building renovation, a backbone extension, an IT room or a wireless project coming up, send us the drawings and the campus cabling standard through request a bid. We’ll send back a bid phased to the academic calendar. General contractors and construction managers on campus work can see how we support your bid and submittals on the general contractor page.
This is the scope as delivered. We don't publish quantities, contract values or schedule details. The photo above shows the city, not the property. We'll add photos of the completed work once the owner clears them for release.