| Client | Horton House |
|---|---|
| Location | San Diego, California |
| Project type | Senior housing renovation, occupied |
| Occupied during work | Yes |
| Building | Senior housing, occupied during construction |
| Scope | Nurse call, Wi-Fi, CATV, cameras, access control |
| Nurse call cutover | Unit by unit, old system live until each tested |
| Phasing | By floor, around meals and care schedules |
| Closeout | Station test log, as-builts, labeling schedule |
| License | CSLB #472017, C-7 Low Voltage Systems |
Horton House: five low voltage systems in occupied senior housing
Horton House is a senior housing building in San Diego that was renovated while its residents kept living there. Our low voltage scope covered five systems: a nurse call system, property-wide Wi-Fi, CATV distribution, surveillance cameras and access control.
Senior housing comes with constraints an empty building doesn’t have. The residents were older, some used mobility aids, and the work had to fit around the building’s daily routine of meals, activities and staff rounds. The nurse call system set the sequence, because a unit with an out-of-service pull cord has no way to reach staff. So the plan was built around keeping the call system in service while the systems were replaced. We also had to keep dust and noise out of occupied areas during meals, medication passes and scheduled activities, and leave each unit clean when the crew moved on. Telelink Business Services is a licensed C-7 Low Voltage Systems Contractor, CSLB License #472017. Our approach to senior and assisted living work is based on this project.
What we installed at Horton House
Nurse call system. We installed a nurse call and emergency call system with stations in the units, corridor annunciation and a staff annunciation point. It went in to the manufacturer’s listing and the specification, and we tested it station by station from the pull to the annunciator.
Property-wide Wi-Fi. A managed wireless network covering the units and common areas. We designed it from a site survey of the building, cabled it from the riser closets to each access point location, and configured it to keep resident traffic separate from staff traffic.
CATV distribution. A documented MDU distribution system from the headend through riser trunks and floor taps to each unit, built for the video provider’s signal.
Surveillance cameras. Cameras went at entries and in common areas only, not inside units. They recorded to a system property staff could view, and we documented each camera’s manufacturer and model.
Access control. We installed readers, controllers, power supplies and credentials at the common doors and integrated them with the door release. Electrified door hardware was coordinated with the project’s door hardware scope.
Power and network room circuits were the electrician’s scope.
How the work was phased
Before we mobilized, we worked out the sequence with the building’s management. That covered which hours were open for noisy work, which were off limits for meals and activities, how residents would be notified, and how the crew would enter units. We agreed that a runner would knock ahead of the crew and that crew members wouldn’t enter an occupied unit alone.
Risers and pathways came first. The plan was to open each closet once and pull the backbone, the coax trunks and the nurse call corridor wiring in that one visit. Next, we installed the nurse call head end and brought it live alongside the call system the building was still using. Then we converted units one at a time. The new stations were installed and tested on the new head end, and each unit stayed on the old system until the new station tested out.
Wherever possible, we combined the Wi-Fi, coax and data work in each unit into a single scheduled visit to cut down on trips into each unit. We contained corridor ceiling openings with drop cloths and HEPA vacuums, kept drilling to the agreed windows, and wiped down each unit before moving on. Cameras and access control panels were cut over door by door to keep entries secured during the transition, and staff were trained on the systems before turnover. Our occupied building guide describes how we handle notification and scheduling.
What the owner received at closeout
At turnover the owner received:
- A nurse call test log recording every station tested from the unit to the annunciator.
- Test results for the copper drops and signal level readings for the CATV distribution.
- As-built drawings showing nurse call stations, access points, cameras, outlets and equipment locations.
- A labeling schedule matching the labels on every outlet, panel and cable, following TIA-606.
- The manufacturer and model list for every installed system.
- The access control credential database and administrator training for management staff.
- Manufacturer documentation and warranty letters for the installed systems.
Next step
If you operate senior housing or assisted living and need a nurse call conversion, Wi-Fi, cameras or entry systems with residents in place, we’re happy to take a look. Send the drawings and the building’s working-hour rules through request a bid, and we’ll send back a bid phased by floor. General contractors on senior housing renovations can see how we fit into your schedule on the general contractor page.
This is the scope as delivered. We don't publish quantities, contract values or schedule details. The photo above shows the city, not the property. We'll add photos of the completed work once the owner clears them for release.