| Client | Little Tokyo Towers |
|---|---|
| Location | Los Angeles, California |
| Project type | Multifamily renovation, occupied building |
| Occupied during work | Yes |
| Building | Multifamily, occupied during construction |
| Scope | Wi-Fi, CATV, cameras, access control |
| Phasing | Risers first, then unit by unit by stack |
| Closeout | Test results, as-builts, labeling schedule |
| License | CSLB #472017, C-7 Low Voltage Systems |
Little Tokyo Towers: four building-wide systems in an occupied rehab
Little Tokyo Towers is a multifamily building in Los Angeles that was renovated with residents in place. Our part of the renovation covered four building-wide low voltage systems: property-wide Wi-Fi, CATV distribution, surveillance cameras and access control.
The job meant adding systems that touch every unit and every common door without relocating anyone. We planned the changeover to keep entry and television service running, and we scheduled unit entry on notice, with the resident present. The closeout included the documentation the owner’s lender, compliance staff and property manager would ask for after turnover. Telelink Business Services is a licensed C-7 Low Voltage Systems Contractor, CSLB License #472017. This project is one of the occupied rehabs our multifamily and affordable housing approach is built on.
What we installed at Little Tokyo Towers
Property-wide Wi-Fi. A managed wireless network reaching the units and the common areas. In a multifamily building, that meant cabling from the riser closets to access point locations we chose from a site survey of the walls and corridors. It also meant network equipment in the closets and the main room, configured so the property can manage the network as one system. Our wireless networks page describes the design approach.
CATV distribution. A documented MDU distribution system from the headend through riser trunks and floor taps to an outlet in each unit, built to accept the video provider’s signal and installed to California Electrical Code Article 820.
Surveillance cameras. Cameras at entries and in common areas, cabled to a recorder property staff could view. We documented each one by manufacturer and model for the owner’s file.
Access control. We installed readers, controllers, power supplies and credentials at the common doors and integrated them with the door release. Electrified door hardware was coordinated with the project’s door hardware scope, which falls outside the C-7 license.
Line voltage and network room power were the electrician’s scope.
How the work was phased
With people living in the building, the building set the sequence and we worked within it. The risers were the only vertical pathway, so they came first. We surveyed the closets, removed abandoned cable where the scope called for it, firestopped the penetrations, and pulled backbone fiber and coax trunks together to limit trips into each closet.
The network rooms and the CATV headend came next, so each floor could go live as soon as its units were done. We scheduled unit work by stack. The property manager sent the notices, and a runner knocked ahead of the crew. We planned each unit’s wireless, coax and data work as a single visit with the resident present, and the rule was that crew members didn’t enter an occupied unit alone.
We installed the common-area cameras and access control panels alongside the existing systems, then cut them over door by door to keep releases working and lobbies covered during the switch. Wi-Fi went live floor by floor. Before turnover, we trained property staff on the camera client, the access control platform and the wireless dashboard. The sequence matches the one in our occupied building guide.
What the owner received at closeout
The owner’s closeout package included:
- Test results for every copper drop and signal level readings for the CATV distribution.
- As-built drawings showing access point, camera, outlet and equipment locations.
- A labeling schedule matching the labels on every outlet, patch panel and cable, following TIA-606.
- The manufacturer and model list for cameras, recorder, switches and access points.
- The access control user and credential database handed to property management, with administrator training.
- Manufacturer documentation and warranty letters for the installed equipment.
Next step
If you own or manage an occupied multifamily building that needs Wi-Fi, CATV, cameras or entry systems, send over the drawings and the resident notice lead time through request a bid. We’ll send back a bid phased by stack. General contractors carrying Division 27 and 28 on a rehab can see how we fit into your schedule on the general contractor page.
This is the scope as delivered. We don't publish quantities, contract values or schedule details. The photo above shows the city, not the property. We'll add photos of the completed work once the owner clears them for release.